Hwy 351 Green County-AHTD

This project shall consist of grading and drainage to improve an existing county road. The counties officials worked to receive a federal grant to improve the county road and make it a safer route. The new road will have an improved alignment by reducing the steep grades and widening the traveled way. There is approximately 64,000 cubic yards of compacted dirt and several hundred feet of drainage culverts. The project is scheduled to be completed in late summer of 2015.

Vitals:

Size:
64,000 cubic yards
Value:
$1,328,906.00
RCI Role:
General Contractor
Completion:
Summer 2015
   |